Friday, April 12, 2013

Hodge Hall: Week 48 -- The view from my desk

Cloudy and cool today, but it's been mostly springlike this week.

Lots of hauling and lifting going on at the Hodge Hall construction site.

We have another large crane on the site now. This one is being used by the masonry company to lift concrete block to the upper levels. The forklift can only reach so far. You can see the hydraulic scaffold on the outside of the fifth level at the corner.

On the Fee Lane side, workers have been using another crane and an aerial lift to deliver materials to the upper floors -- insulation, pipes, frames for walls. Railing and steps for one of the stairwells also was delivered this week.

On the ground floor, workers have built wooden forms for the sloped classroom floor.