Friday, August 17, 2012

Hodge Hall: Week 14 -- The view from my desk

Holes where footings will go for the Hodge Hall expansion are filled with rain from the much-needed storm we had Thursday night. A worker sets up surveying equipment on the 10th Street side of the site.

The second phase of the Hodge Hall Undergraduate Center expansion was delayed a little this week because of some paperwork, but the crew from Gibraltar Construction was on site today looking at the lay of the land.

Gibraltar will be pouring the cement for the concrete footings that will hold the steel beams. The concrete work is expected to take place through Sept. 21. We'll start seeing steel arrive in mid-September.